The Vale progresses, naysayers silenced

By 21st March 2009April 21st, 2021Niseko News, Niseko Real Estate

WHILE the leaves on the trees are yet to sprout, the recommencement of work on The Vale construction site is a sure sign spring is on the way. Nisade Chairman Jonathan Martin said he was happy to silence the naysayers with the recommencement of the construction. "This will put to rest the endless and unfortunate rumours that the site is not proceeding," Martin said. The world economic crisis has put pressure on Niseko developers, and there has been speculation The Vale may become a casualty mid-way through construction.
Martin said that with completion scheduled for December 6, work would reach capacity in early April with the first concrete pour. After that, the structure would go up at the rate of a one storey every two weeks, so by August the ‘bones’ of the building would be up, he said.